401.01 |
Project Management |
BoE DocDB # |
Supporting docs |
|
401.01.01 | Project Management Milestones and Interfaces | |||
401.01.02 | Project Management & Administration | 11644 | ||
401.01.03 | Project Controls & Finance | 11645 | ||
401.01.04 | Project Office Support | 11646 | ||
401.02 |
Hadron Calorimeter (HCAL) Upgrade |
BoE DocDB # |
Supporting docs |
|
401.02.01 | HCAL Milestones and Interfaces | |||
401.02.02 | HCAL Management | 11743 | ||
401.02.03 | HF Front-End | |||
401.02.03.01 | —— Milestones and Interfaces | |||
401.02.03.02 | —— PMT Signal Cables (OFF-PROJECT) | 11691 | 11633 | |
401.02.03.03 | —— QIE10 ASIC | 11616 | 12027 | |
401.02.03.04 | —— Front-End System Design and Prototyping | |||
401.02.03.04.01 | ——— Prototype HF Crate | 11695 | 11771 | |
401.02.03.04.02 | ——— Prototype HF QIE Card | 11696 | 11621 | |
401.02.03.04.03 | ——— Prototype HF ngCCM | 11697 | 11889 | |
401.02.03.04.04 | ——— Prototype HF Calibration Module | 11698 | 11963 | |
401.02.03.04.05 | ——— HF Frontend Prototype System Testing | 11699 | 11881 | |
401.02.03.05 | —— Front-End Crates and Backplanes (OFF-PROJECT) | 11636 | ||
401.02.03.06 | —— QIE Cards (OFF-PROJECT) | 11676 | ||
401.02.03.07 | —— Calibration System | 11677 | 11965 | |
401.02.03.08 | —— HF ngCCM | 11678 | 11890 | |
401.02.03.09 | —— Low Voltage System Upgrade | 11679 | 11882 | |
401.02.03.10 | —— Optical Fiber Plant | 11637 | 11883 | |
401.02.03.11 | —— HF Cable Adapter Boards | 11710 | 11884 | |
401.02.03.12 | —— HF Testing & Burn-In | 11680 | 11885 | |
401.02.03.13 | —— HF Front-End Installation | 11681 | 11886 | |
401.02.04 | HB/HE Front-End | |||
401.02.04.01 | —— Milestones and Interfaces | |||
401.02.04.02 | —— SiPM | 11660 | 11848 | |
401.02.04.03 | —— Optical Decoder Unit | 11618 | 11634 | |
401.02.04.04 | —— SiPM Control Board | 11638 | 11938 | |
401.02.04.05 | —— QIE11 ASIC SiPM Version | 11630 | 11632 | |
401.02.04.06 | —— Radiation Hard FPGA | 11711 | 11998 | |
401.02.04.07 | —— QIE Cards | 11639 | 11994 | |
401.02.04.08 | —— Calibration System | 11640 | 11995 | |
401.02.04.09 | —— HB/HE ngCCM | 11661 | 11993 | |
401.02.04.10 | —— Cooling System | 11662 | 11900 | |
401.02.04.11 | —— Readout Module Mechanics | 11663 | 11900 | |
401.02.04.12 | —— Integrated Readout Modules | 11641 | 11901 | |
401.02.04.13 | —— Detector Safety System | 11664 | 11778 | |
401.02.04.14 | —— Low Voltage | 11665 | 3647 | |
401.02.04.15 | —— RBX Level Testing & Burn-In | 11666 | 11902 | |
401.02.04.16 | —— HB/HE Installation & Commissioning | 11667 | 11903 | |
401.02.05 | HCAL Back-End | |||
401.02.05.01 | —— Milestones and Interfaces | 11787 | ||
401.02.05.02 | —— uHTR Design & Firmware | 11674 | 11941 | |
401.02.05.03 | —— uHTR HF (OFF-PROJECT) | 11693 | ||
401.02.05.04 | —— uHTR HB/HE | 11647 | 11648 | |
401.02.05.05 | —— AMC13 | 11650 | 11649 | |
401.02.05.06 | —— MicroTCA Crates | 11654 | 11651 | |
401.02.05.07 | —— MicroTCA Control Hub (MCH) | 11655 | 11652 | |
401.02.05.08 | —— MicroTCA Power Module | 11656 | 11653 | |
401.02.05.09 | —— MicroTCA AC/DC Converter | 11668 | 11702 | |
401.02.05.10 | —— Integrated HF MicroTCA Crates | 11669 | 11942 | |
401.02.05.11 | —— HF MicroTCA Installation & Commissioning | 11670 | 11945 | |
401.02.05.12 | —— Optical Splitters | 11671 | 11719 | |
401.02.05.13 | —— Integrated HB/HE MicroTCA Crates | 11672 | 11943 | |
401.02.05.14 | —— HB/HE MicroTCA Installation & Commissioning | 11673 | 11944 | |
401.02.05.15 | —— HCAL/Trigger Connection Optics | 11868 | 11869 | |
401.03 |
Forward Pixels (FPIX) Detector Upgrade |
BoE DocDB # |
Supporting docs |
|
401.03.01 | FPIX Milestones and Interfaces | |||
401.03.02 | FPIX Management | 11744 | ||
401.03.03 | FPIX Components | |||
401.03.03.01 | —— Module | |||
401.03.03.01.01 | ——— Sensor | 11614 | ||
401.03.03.01.02 | ——— Bump Bonding | 11704 | ||
401.03.03.01.03 | ——— Pixel Module Assembly & Testing | 11730 | ||
401.03.03.02 | —— Electronics | |||
401.03.03.02.01 | ——— Pixel Readout Chip | 11705 | ||
401.03.03.02.02 | ——— Token Bit Manager (TBM) & Other ASICs | 11706 | ||
401.03.03.02.03 | ——— High Density Interconnect (HDI) | 11708 | ||
401.03.03.02.04 | ——— Port Card | 11709 | ||
401.03.03.02.05 | ——— Cables. Connectors & Fibers | 11714 | ||
401.03.03.02.06 | ——— Pixel Optohybrid (POH) | 11723 | ||
401.03.03.02.07 | ——— Power Supply System | 11724 | ||
401.03.03.02.08 | ——— DAQ Hardware | 11725 | ||
401.03.03.03 | —— Mechanical Structures and Cooling | |||
401.03.03.03.01 | ——— Half Disk Mechanics | 11726 | ||
401.03.03.03.02 | ——— Half Cylinder | 11727 | ||
401.03.03.03.03 | ——— Cooling Tubes | 11728 | ||
401.03.03.03.04 | ——— Integration & Testing | 11740 | ||
401.03.03.03.05 | ——— Installation Fixture & Testing | 11739 | ||
401.03.04 | FPIX Assembly & Testing | |||
401.03.04.01 | —— Half Disk detector assembly and testing | 11731 | ||
401.03.04.02 | —— Half cylinder detector assembly and testing | 11746 | ||
401.03.04.03 | —— Detector control system (DCS) | 11748 | ||
401.03.04.04 | —— Test Stand and Database | 11747 | ||
401.03.04.05 | —— DAQ development for system test | 11742 | ||
401.03.04.06 | —— Delivery to TIF at CERN | 11736 | ||
401.03.04.07 | —— Reassembly and test at TIF | 11737 | ||
401.03.04.08 | —— Commission test | 11738 | ||
401.03.05 | FPIX Pilot System | |||
401.03.05.01 | —— Pilot System Components | 11735 | ||
401.03.05.02 | —— Test system hardware | 11734 | ||
401.03.05.03 | —— Test system software & database | 11732 | ||
401.03.05.04 | —— FPIX pilot system delivery to CERN | 11729 | ||
401.04 |
Trigger Upgrade |
BoE DocDB # |
Supporting docs |
|
401.04.01 | Trigger Milestones and Interfaces | |||
401.04.02 | Trigger Management | 11745 | ||
401.04.03 | Muon Trigger | |||
401.04.03.02 | —— MUON Port Card Mezzanine (MPCM) | |||
401.04.03.02.01 | ——— MPCM Software and Firmware | 11749 | ||
401.04.03.02.02 | ——— MPCM Production | 11750 | 11922 | |
401.04.03.02.03 | ——— MPCM Test, Install, Commission | 11751 | ||
401.04.03.03 | —— MPC-EMUTF Optical Fibers | 11752 | 11923 | |
401.04.03.04 | —— End-Cap Muon Track-Finder | |||
401.04.03.04.01 | ——— EMUTF Software and Firmware | 11753 | ||
401.04.03.04.02 | ——— EMUTF Production | 11754 | 11924 11925 | |
401.04.03.04.03 | ——— EMUTF Test, Install, Commission | 11755 | ||
401.04.03.05 | —— EMUTF Infrastructure | 11756 | 11926 | |
401.04.03.06 | —— MUON Sorter (MS) | |||
401.04.03.06.01 | ——— MSM Software and Firmware | 11757 | ||
401.04.03.06.02 | ——— MSM Production | 11758 | 11927 | |
401.04.03.06.03 | ——— MSM Test, Install, Commission | 11759 | ||
401.04.03.06.04 | ——— MS-EMUTF Firmware and Software | 11892 | ||
401.04.03.06.05 | ——— MS-EMUTF Test and Commission | 11893 | ||
401.04.04 | Calorimeter Trigger | |||
401.04.04.02 | —— Calorimeter Trigger Processor | |||
401.04.04.02.01 | ——— CTP7 Software and Firmware | 11760 | ||
401.04.04.02.02 | ——— CTP7 Production | 11761 | 11924 11928 | |
401.04.04.02.03 | ——— CTP7 Test, Install, Commission | 11762 | ||
401.04.04.03 | —— Crosspoint I/O Card (CIOx) | |||
401.04.04.03.01 | ——— CIOx Software and Firmware | 11763 | ||
401.04.04.03.02 | ——— CIOx Production | 11764 | 11929 | |
401.04.04.03.03 | ——— CIOx Test, Install, Commission | 11765 | ||
401.04.04.04 | —— CTP Infrastructure | 11766 | 11926 | |
401.04.04.05 | —— Optical Receiver Mezzanines | 11767 | ||
401.04.04.06 | —— oSLB-oRM Optical Fibers | 11768 | ||